Road Work Near LCE

 

The city's contractor, Hardy & Harper will begin roadway repair and resurfacing later this week in the neighborhood of LCE, as noted below:


  • May 19 thru May 27: Concrete curb and gutter repairs along Flanders (Encinas to Loma Vista); Lasheart (north of Flanders); and, Salisbury (Loma Vista to Lasheart). No work will take place on Lasheart, Foothill to Salisbury during this week to minimize impact to school traffic.
  • Week of May 31: Concrete curb and gutter repairs on Lasheart (Foothill to Flanders), Leland and Loma Vista will be performed (school is out).
  • Week of June 6: Pavement grinding and re-paving operation for above noted streets will follow (school remains closed).
  • Post June 10th: Minor striping and sign installation work will be performed, in weeks following.

Streets will remain accessible during curb and gutter repair work. Streets will be CLOSED in segments during the week of June 6th, for paving operations.


For any public inquiries or concerns, City's Public Works staff can assist at 818-790-8882.


At times this schedule may change depending on field conditions; Mrs. Blaney will be told about progress and if anything should change. Thank you for your patience.